12. DENIS FORMULA – REVISION
#4 – METRIC
12.3 CONVERSION TABLES FOR FITTINGS TO BE ADDED
TO LINE TOTAL MEASURED
THROUGH ALL FITTINGS
Print
45 Elbows
| 12.5 mm to 65
mm pipe |
0.47 |
lin. meters
of same size & thickness |
|
| 75 mm to 125 mm pipe
|
0.62
|
"
|
|
| 150 mm to 200 mm pipe
|
0.78
|
"
|
|
| 225 mm to 300 mm pipe
|
0.93
|
"
|
|
| 350 mm to 600 mm pipe
|
1.24
|
"
|
|
| 625 mm to 750 mm pipe
|
1.55
|
"
|
90 Elbows
| 12.5 mm to 65
mm pipe
|
0.62
|
lin. meters
of same size & thickness
|
|
| 75 mm to 125 mm pipe
|
0.93
|
"
|
|
| 150 mm to 200 mm pipe
|
1.24
|
"
|
|
| 225 mm to 300 mm pipe
|
1.55
|
"
|
|
| 350 mm to 600 mm pipe
|
1.86
|
"
|
|
| 625 mm to 750 mm pipe
|
2.17
|
"
|
When stainless steel or FRP
jacketing is specified, factors for elbows (with stainless steel
or FRP covers), multiply the above tables by 2.5
Bent Pipe multiply
length by factor of 3 of same size and thickness
Tracer Loops 0.93 lin. meters minimum, per loop at tracer
(Wrapped Insulation)
size by 25 mm (nominal) thickness
Flanges (Pair)
| – Hot
|
0.93
|
lin. meters
of same size and thickness
|
|
| – Cryogenic
|
2.17
|
"
|
|
| – Anti-condensation
|
1.24
|
"
|
Valve Body (screwed)
| 12.5 mm to 75
mm
|
0.62
|
lin. meters
of same size & thickness
|
|
| 100 mm to 200 mm
|
0.93
|
"
|
|
| 250 mm and over
|
1.24
|
"
|
Valve Body (welded)
| 12.5 mm to 75
mm
|
0.93
|
lin. meters
of same size & thickness
|
|
| 100 mm to 200 mm
|
1.24
|
"
|
|
| 225 mm to 300 mm
|
1.55
|
"
|
|
| 350 mm to 450 mm
|
1.86
|
"
|
|
| 500 mm to 600 mm
|
2.48
|
"
|
|
| 650 mm to 750 mm
|
3.10
|
"
|
|
| 800 mm and over
|
|
measured as
equipment
|
Valve Body (flanged)
| 12.5 mm to 75
mm
|
0.62
|
lin. meters
of same size & thickness(+ flanges)
|
|
| 100 mm to 200 mm
|
0.93
|
"
|
|
| 225 mm to 300 mm
|
1.24
|
"
|
|
| 350 mm to 450 mm
|
1.55
|
"
|
|
| 500 mm to 600 mm
|
1.86
|
"
|
|
| 650 mm to 750 mm
|
2.48
|
"
|
|
| 800 mm and over
|
3.10
|
measured as
equipment
|
Valve Body (with bonnet) Use
appropriate factors as above.
| 12.5 mm to 75
mm
|
And
|
0.62 |
lin. meters
of same size & thickness
|
|
| 100 mm to 200 mm
|
"
|
0.93 |
"
|
|
| 350 mm to 450 mm
|
"
|
1.24 |
"
|
|
| 550 mm to 750 mm
|
"
|
1.55 |
"
|
|
| 800 mm and over
|
"
|
1.86 |
"
|
Tees .62 lin. meters of same size and thickness
Branch
Fittings 0.62 lin. meters of same size and thickness
Reducers,
Caps and Termination Points 0.47 lin. meters of same size and
thickness
*Hangers (hot) 0.31 lin. meters of same size and
thickness
*Including shoe supports and brackets. Excludes
guides and anchors.
Hangers (cryogenic/anti-condensation)
0.31 lin.
meters of same size and thickness
Removable Covers multiply fitting
factors by 2.5, or a price per cover established by tender.
Screwed
/ FRP Fittings:
Specified flexible insulation, multiply all factors
by 2. Specified preformed or rigid insulation
multiply all
factors
by 3.
Vitaulic Fittings:
These fittings require special consideration because
of size and complexity. Therefore the conversion table factors
are to be multiplied as follows:
| 45 Elbows
|
Multiply factors
3 times |
|
| 90 Elbows
|
Multiply factors 3 times |
Tees, Fittings:
| 12.5 mm to 125
mm
|
Multiply factors
3 times
|
|
| 150 mm to 300 mm
|
Multiply factors 5 times
|
|
| 350 mm and over
|
Multiply factors 7 times
|
Penetrations:
Items which interfere with the insulation system, e.g., conduits,
handrails, ancillary hangers, uninsulated pipe or tubing, etc.
Each
cut out 0.62 lin. meters of same size and thickness
When penetrations
occur at fittings:
Each cut out 0.93 lin. meters of same size
and thickness
Obstructions
Where insulation thickness has to
be shaved or cut for walls, sleeves, equipment or other interferences:
Multiply
the length of interference by factor of 2
HEIGHT ALLOWANCES
Height Factor Above Grade*
Factor to increase unit
price for over 9.2 m height by 10%
Factor to increase unit price for over 12.2 m height by 20%
Factor to increase unit price for over 15.3 m height by 30%
Factor to increase unit price for over 18.3 m height by 40%
Factor to increase unit price for over 21.4 m height by 50%
Factor to increase unit price for up to 24.4 m height by 60%
Factor to increase unit price for over 27.5 m height by 70%
plus 3% per additional meter of height
*Grade does not include working
platforms
HOT WORK: (When insulation applied to line in
service above 65°C
operating temperature)
| 12.5 mm to 65
mm pipe
|
increase labour
component by
|
25%
|
|
| 75 mm to 125 mm pipe
|
"
|
35%
|
|
| 150 mm to 200 mm pipe
|
"
|
45%
|
|
| 225 mm to 350 mm pipe
|
"
|
60%
|
|
| 375 mm to 500 mm pipe
|
"
|
75%
|
|
| over 500 mm pipe
|
"
|
100%
|
If labour component has not been identified apply
only 50% of the above to the unit prices. These percentages are
to compensate for loss of productivity, however safe working conditions
shall take precedent.
Imperial Measurement (Conversion)
For equivalent
fitting factors multiply computations by 3.28 |