6. COMMERCIAL DUCTWORK AND PLENUM

6.2 FINISHES

B. ROUND DUCTS

INSULATION ON CONCEALED DUCT WORK WILL BE LEFT AS FACTORY FINISHED WITH NO FURTHER FINISH REQUIRED.

The following finishes apply to exposed duct work only.

Specification
Code No.

 
   

CRD/1

Indoor

   

 

– Use flexible insulation with integral vapour retarder. At all joints and breaks, apply vapour retarder tape.

– Apply treated fabric jacket over insulation using fabric adhesive and finish with one (1) coat of fabric coating.

   

CRD/2

Indoor

   

 

 

– Use scored rigid insulation with integral vapour retarder on ductwork 600 mm diameter and larger.

– Use flexible insulation with integral vapour retarder on ductwork smaller than 600 mm diameter. At all joints and breaks, apply vapour retarder tape.

– Apply treated fabric jacket over insulation using fabric adhesive and finish with one (1) coat of fabric coating.

   

CRD/3

Indoor

   

 

– Use flexible insulation with integral vapour retarder.

– At all joints and breaks, apply vapour retarder tape.

   

CRD/4

Outdoor

   

 

 

– Adhere vapour retarder tape over all joints and breaks in vapour retarder on cold or dual temp ductwork.

– Apply over the insulation surface a stucco embossed aluminum jacket secured with pop rivets. All joints sealed or flashed to shed water.

   

CRD/5

Outdoor

   

 

– Apply to the insulation surface a coat (minimum 1 litre per 1.5 m) of weather coating. While still wet, embed a layer of reinforcing membrane and finish with a final coat (minimum 1 litre per 1.5 m) of weather coating. (Insulation having factory applied vapour retarder is not required with this finish).